Required intervals at a glance
The recurring obligations for a PSM and RMP covered ammonia refrigeration facility. All are minimums; a facility can and often should do them more often.
| Requirement | Citation | Interval |
|---|---|---|
| Process hazard analysis revalidation | 29 CFR 1910.119(e)(6) | At least every 5 years |
| PSM compliance audit | 29 CFR 1910.119(o)(1) | At least every 3 years |
| Operator refresher training | 29 CFR 1910.119(g)(2) | At least every 3 years |
| RMP resubmission | 40 CFR 68.190(b) | At least every 5 years |
| RMP compliance audit | 40 CFR 68.58 / 68.79 | At least every 3 years |
| Mechanical integrity inspections | 29 CFR 1910.119(j)(4), IIAR 6 | Per RAGAGEP, typically annual and 5-year |
Deadline questions
How often is a PSM compliance audit required?
At least every three years under 29 CFR 1910.119(o)(1). The clock runs from the completion date of the previous audit, and the two most recent audit reports must be retained. RMP-covered facilities have a parallel three-year audit requirement under 40 CFR 68.58 (Program 2) or 68.79 (Program 3).
How often must a PHA be revalidated?
At least every five years under 29 CFR 1910.119(e)(6). The revalidation must be as thorough as the original PHA, and it is a good time to fold in management-of-change records and incident findings from the intervening years.
When does the RMP need to be resubmitted?
A complete RMP must be resubmitted at least every five years from the date of the last complete submission (40 CFR 68.190). Some events require an earlier update, including a change in program level, a change that alters the worst-case scenario, or a new covered process.
How often is refresher training required?
At least every three years under 29 CFR 1910.119(g)(2), and more often if the employer, in consultation with the operators, determines it is needed. Refresher training must be documented with the date, the employee, and the means used to verify understanding.
Related tools
Deadlines assume you are covered. If that is not settled yet, start here.
Does OSHA PSM and EPA RMP apply to your facility?
OpenThe triennial audit, performed the way OSHA performs it.
OpenFive-year resubmissions and everything that triggers an earlier one.
OpenMechanical integrity intervals under the current edition.
OpenOperating an ammonia refrigeration facility?
NH3Edge provides OSHA PSM and EPA RMP compliance consulting for ammonia refrigeration facilities — third-party compliance audits, ammonia inventory determination, and continuous real-time inventory monitoring. Based in Salt Lake City, serving facilities nationwide.